What happened this week in the field.
Phase 2 Update:
- Well 1 – Sales
- Well 2 – Sales
- Well 3 – Waiting to frack.
- Well 4 – Flow back complete. Adding flow lines and oil tanks then put into sales.
- Well 5 – Finishing up the lateral drilling.
Phase 3 Update:
- Well 1 – Waiting to frack.
- Well 2 – Fracked. We shut in the well to let the frack fluids settle in the formation. We follow up with a flow back of the frack fluids for 2-3 weeks. Then we put the well in sales.
- Well 3 – Figuring out the frack recipe.
- Well 4 – Prepping site.
We will be out at the field on Wednesday of next week if you would like to meet us out at the field.